Integration tree follows a monthly release cycle
From OMAPpedia
(Difference between revisions)
m (Added category tag) |
|||
| (One intermediate revision not shown) | |||
| Line 16: | Line 16: | ||
Finally proceed to give the Sync tree for handoff. | Finally proceed to give the Sync tree for handoff. | ||
| - | [[category: | + | [[category:Linux]] |
| + | [[Category:Patches and Release]] | ||
Latest revision as of 14:02, 25 May 2010
Sync Tree Release model based on Moving Code base
Phase I: Developers are submitting patches to various mailing lists/Gerrit etc
Phase II: 3 Days before the Code freeze, we take the Snapshot of Moving code base, Freeze it and merge patches from Phase I (which are not in code base yet)
Sources of these patches are the patches in submitted-but-not-accepted state
Sometimes patches/features in development required for a Monthly release
Phase III: Subject the sync tree to Unit testing and fix any issues found in a week.
Finally proceed to give the Sync tree for handoff.